Projetcs  
     
 
       
  Nilai Stadium    
 

In 2004, KUB Builders (formerly known as Ibuzawa Corporation) rescued the Nilai Stadium project. The Nilai Stadium was built as the main venue for the Sukan Malaysia (SUKMA) Games 2004. The original main contractors were terminated for non-performance and KUB Builders (formerly known as Ibuzawa Corporation) was given a time schedule of 100 days to complete the stadium in time for the games.

As the only contractor courageous enough to undertake the job under those preposterous terms, we went to work immediately with our sleeves rolled up. To cut a long story short, the Nilai Stadium was handed over to the Negeri Sembilan state government after 77 days – a full 23 days before the deadline!

 
 

The 77-Day Mission Impossible

Contract Value : RM22 million